Upper Trishuli-1, one of the largest FDI projects, achieves 22% physical progress

Image Source: NWEDC
Image Source: NWEDC

With 70% of the project cost being debt financed by nine international banks and 30% from private investments through NWEDC, the project is expected to be completed by December 2026. The installed capacity is 216 MW.

-the_farsight |

Considered one of the largest FDI projects in Nepal to date, the Upper Trishuli-1 hydroelectric project has reportedly achieved 22% physical progress since its commencement in January 2022. The project recently completed the construction of a 420 metres long diversion tunnel and works are now underway on the construction of the head works.

Located in the Rasuwa district of Bagmati Province, about 75 kilometres northwest of Kathmandu, Upper Trishuli-1 has an installed capacity of 216 megawatts. The expected date of completion is December 2026.

The estimated project cost of Upper Trishuli-1 stands at $647.3 million. 

70% of the project costs i.e., $453.2 million is financed by a consortium of nine different international banks which include the International Finance Corporation (IFC), Asian Development Bank (ADB), Asian Infrastructure Investment Bank (AIIB), Export-Import Bank of Korea (K-EXIM), Korea Development Bank (KDB), Commonwealth Development Corporation (CDC), FMO (a Netherlands’ development bank), Proparco (a French finance development institution), and OPEC Fund for International Development (OFID).

The remaining 30% of the cost is financed through a special purpose vehicle — Nepal Water & Energy Development Company (NWEDC) with equity-sharing among a Korean consortium — consisting of Korea South East Power (KOEN), Daelim, Kyeryong; the IFC and a local partner.

Upon completion, the entire production from the project will be bought by the Nepal Electricity Authority (NEA) under a 30-year Power Purchase Agreement (PPA) with the NWEDC that was reached in January 2018. The rate per unit has been set at Rs 4.80 during the wet season (June-November) and at Rs 8.40 during the dry season (December-May).

According to the PPA, the NEA will pay the NWEDC in US dollars for a period of 10 years or until the foreign debt has been repaid, following the exchange rate prevailing on the day the agreement was signed.

the_farsight Business | Finance | Environment | Econmy | Politics | Insight | In-depth Analysis | News | Investigation | Research | Expert Opinion | Anatomy of Complex Issues

Read More Stories

Market

NEPSE retreats after six-day winning streak

The Nepal Stock Exchange (NEPSE) ended its six-day rally on Wednesday, with the...

by the_farsight

News

25 die of altitude sickness in Annapurna region in 2025/26, 12 Nepalis

A total of 25 tourists died from altitude sickness while travelling in the...

by the_farsight

News

Today's weather update: Heavy rainfall alert issued for several provinces

Monsoon conditions remain active across the country today, with the monsoon trough positioned...

by the_farsight

×